How many copies should we print? A four-step uncertainty register

· · Worked example and worksheet

The print shop needs an order by noon on Thursday. The repair meetup takes place on Saturday, and people can walk in without registering. The coordinator can order 20 instruction sheets now and buy extras, or pay for 40 up front. What could she learn before noon that would actually change her order?

1. Count teams at the workbench

In this fictional meetup, each repair team can take one sheet to its workbench. Two people fixing one lamp together need one sheet. A visitor bringing two lamps to the same bench also needs one. A headcount, an item count and a print quantity could all be different. The repair meetup data dictionary shows how to write a counting rule the next volunteer can use.

The coordinator pencils in 24 teams if only confirmed benches fill, and up to 34 if all the walk-in spaces fill too. Those are planning cases. They give her two orders to price without requiring her to guess how likely either turnout is.

2. At 28 sheets, the quotes tie

Suppose offer A is $30 for 20 sheets plus $2.50 for each extra sheet ordered individually. Offer B is $50 for 40. Both quotes cover identical sheets and collection, with no other fees. Below 20 copies, A still costs its $30 minimum. The comparison covers demand up to 40 sheets.

What each fictional offer costs if the extra copies arrive in time
Copies neededOffer AOffer B
24$40$50
28$50$50
34$65$50

There is a $20 gap between the opening prices. Eight extra sheets at $2.50 use up that gap. At 28 copies the prices tie. At 29 the smaller opening order costs $52.50. HM Treasury calls a boundary that changes which option is preferred a switching value. Here the boundary compares the printing bill alone.

3. Check who can promise the extra copies

The $40 figure at 24 assumes the printer can supply four extras when they are needed. The $65 figure at 34 assumes it can supply fourteen. Suppose the printer can guarantee only six extras by Saturday opening. A can then cover at most 26 teams, even if the coordinator is willing to spend more. If 27 teams arrive, one team goes without a sheet.

Give the print liaison one question for Thursday at 10:00: “How many additional sheets can you have here before the benches open, and when must you have our final count?” Record the answer alongside the quote. If the printer needs that count on Friday, Saturday walk-ins still have to be allowed for in Friday’s order. Whoever counts bookings cannot promise the printer’s capacity.

4. Write the decision before the deadline

In the worked case, the booking lead still has an upper estimate of 34 on Thursday morning. The liaison confirms the six-extra limit and a Friday collection for the 40-sheet batch. Serving every team in that planning range takes priority. The coordinator orders B at 11:30 for $50. If only 24 teams arrive, 16 sheets will be left. That foreseeable waste belongs in the decision record too.

Download the print-order uncertainty register (CSV) for the two completed checks and the order decision. At your event, replace the estimates, deadlines and names of the responsible roles. If neither quote can cover the agreed range by opening, the coordinator needs another supply arrangement before marking the order decided. Afterwards, record how many teams wanted a sheet, including requests you could not fill. Otherwise a stack that ran out at 26 looks exactly like demand for 26.

Next reading: Map who can make each decision at a repair meetup when a plan depends on somebody outside the organizing team.